Regional Water Supply Pipeline Budva – Tivat
The main design of the pipeline of the Regional Water Supply System of the Montenegrin coast, on the route Budva – Tivat

Development of the main design of the pipeline of the Regional water supply system on the route Budva – Tivat was preceded by a detailed hydraulic analysis (which was also done by our team of experts), with the aim of selecting the optimal solution.
We have developed the selected solution to the level of the main design. A pipeline approximately 11 km long is planned. The connection of the planned pipeline is planned at the end of the pipeline breaking chamber Prijevor – Lastva Grbaljska. The planned pipeline ends with the connection to the existing branch of the Regional Water Supply System “Gradiošnica”.
More in this category
Fire Hydrant Networks in Bar – Boljare Highway Tunnels
Main design · Ministry of Transport and Maritime Affairs
Water Supply System for Tivat – Jaz Boulevard
Main design · Municipality of Kotor