The main designs of a hydrant network for tunnels on the Smokovac – Mateševo section

Awesome Image

  • Client:
    Vlada Crne Gore, Ministarstvo pomorstva i saobraćaja
  • Date:
    2016-2018
  • Budget:
  • Location:
    Montenegro

This project included the preparation of the main designs of a hydrant network for 13 tunnels on the route of the Bar – Boljare highway, Smokovac – Mateševo section.

The designs included hydraulic simulations of hydrant networks of all tunnels, sizing of reservoir volume, design of construction of all reservoirs, selection and sizing of pumping stations that provide the required pressure on each hydrant, construction of pipeline projects in tunnels … The total length of all pipelines is approx. 36 km.