Review of the Main Design of the Berane WWTP
Revision of the WWTP main design in Berane

Nik Com’s team of experts reviewed complex technical documentation as part of the main design of the wastewater treatment plant (WWTP) in Berane. The WWTP capacity is 27,000 population equivalents (ES).
The main project of the wastewater treatment plant (WTP) in Berane Municipality consists of the following 11 books:
BOOK 1 – TECHNOLOGY PROJECT BOOK 2 – HYDROTECHNICAL PROJECT • Volume 2.1 – Main project of internal and external hydro-technical installation for the building • Volume 2.2 – The main project of the water supply infrastructure for the connection of the WWTP • Volume 2.3 – The main project of watercourse regulation, Makva 2 • Volume 2.4 – The main project for the protection of the WWTP plateau • Volume 2.5 – The main project of securing the left bank of Lim within the WWTP site • Volume 2.6 – Main project of internal and external hydro-technical installations, guard house, laboratory, workshop BOOK 3 – MACHINE PROJECT BOOK 4 – HIGH CURRENT ELECTRICAL PROJECT • Volume 4.1 – Main project of electrical installations for WWTP • Volume 4.2 – The main project of the transformer station 10/0.4 kVA and connecting 10kV lines BOOK 5 – ELECTRICAL PROJECT OF WEAK CURRENTS BOOK 6 – ARCHITECTURE AND CONSTRUCTION PROJECT • Volume 6.1 – The main project of the architecture of the administrative building, workshop and guardhouse • Volume 6.2. – The main project of the construction of the administrative building, workshop and guardhouse • Volume 6.3. – The main construction project of the wastewater chamber • Volume 6.4. – The main project of the construction of the levelling tank with the technical bridge • Volume 6.5. – The main design of the construction of the odour removal system • Volume 6.6. – The main design of the mud building construction • Volume 6.7. – The main construction project of the facility for pre-processing • Volume 6.8. – The main design of the construction of the SBR tank • Volume 6.9. – The main design of the WAS tank construction • Volume 6.10. – The main project of the embankment of the plateau
BOOK 7 – LEVELLING AND ROAD PROJECT BOOK 8 – PROJECT OF THERMOMECHANICAL INSTALLATIONS BOOK 9 – ELABORATION AGAINST FIRE PROTECTION BOOK 10 – REPORT ON SAFETY AND HEALTH AT WORK BOOK 11 – PROJECT OF ORGANISATION AND CONSTRUCTION TECHNOLOGY
More in this category
Podgorica Wastewater Treatment System
Conceptual and main design · Capital City of Podgorica · ~€50 million
Technical Acceptance of the Kotor and Tivat WWTP
Technical acceptance · Water and Sewerage PE Tivat and Kotor · €12.2 million